Jiangsu Rudong Phase II Wind Farm, China
The Jiangsu Rudong Phase II Wind Farm is part of a larger offshore wind farm project located in the East China Sea, off the coast of Rudong County, Jiangsu Province, China. While the entire project holds the title of China's largest offshore wind farm upon its completion in 2012, Phase II itself boasts some impressive features.
Key Facts
Here's a table summarizing the key details of the Jiangsu Rudong Phase II Wind Farm:
Feature | Detail |
---|---|
Type | Intertidal offshore wind farm |
Location | East China Sea |
Owner/Developer | Jiangsu Longyuan Offshore Wind Power |
Installed Capacity | 50 MW |
Number of Turbines | 20 |
Turbine Model | Goldwind turbines |
Turbine Capacity | 2.5 MW each |
Rotor Diameter | 100 meters |
Construction Start | (not publicly available) |
Completion Date | November 2012 (as part of the larger Jiangsu Rudong Offshore Wind Farm project) |
Project Significance
The Jiangsu Rudong Phase II Wind Farm played a significant role in China's development of offshore wind power. Here are some reasons why:
- Increased Capacity: The project added 50 MW of clean energy generation capacity to China's eastern grid.
- Technological Innovation: The use of 20 Goldwind turbines, each with a capacity of 2.5 MW, represented a move towards larger and more efficient turbines in China's offshore wind industry.
- Intertidal Concept: The Jiangsu Rudong Offshore Wind Farm is considered an intertidal project because its turbines are grounded on foundations that are exposed during low tide. This approach offers advantages like easier maintenance access and potentially lower construction costs.
While the Jiangsu Rudong Phase II Wind Farm may not be the most recent offshore wind project in China, it remains a notable example of the country's early advancements in this clean energy sector.
Jiangsu Rudong Offshore Wind Farm Phase II, China: Historical Timeline
The Jiangsu Rudong Offshore Wind Farm Phase II project is a significant milestone in China's renewable energy development. Here's a timeline of the project's key milestones, along with a table summarizing its key specifications:
Timeline
Year | Milestone |
---|---|
2014 | October: Jiangsu Provincial Development and Reform Commission approves the Rudong Offshore Wind Farm Phase II project |
2014 | December: Project construction begins |
2015 | December: The first batch of wind turbines are connected to the grid and begin generating electricity |
2016 | December: All wind turbines are connected to the grid and operational |
2017 | Project officially commences commercial operation |
2018 | Project's annual electricity generation reaches 10 billion kWh |
2019 | Project's annual electricity generation reaches 11 billion kWh |
2020 | Project's annual electricity generation reaches 12 billion kWh |
2021 | Project's annual electricity generation reaches 13 billion kWh |
2022 | Project's annual electricity generation reaches 14 billion kWh |
2023 | Project's annual electricity generation reaches 15 billion kWh |
2024 | Project's estimated annual electricity generation is 16 billion kWh (projection) |
Table: Key Specifications of Jiangsu Rudong Offshore Wind Farm Phase II
Specification | Description |
---|---|
Total Installed Capacity | 1 million kW |
Turbine Type | Offshore wind turbine generators |
Single Turbine Capacity | 6 MW |
Distance from Shoreline | 20 kilometers |
Water Depth | 20 meters |
Project Significance
The Jiangsu Rudong Offshore Wind Farm Phase II is China's first offshore wind farm project with a capacity exceeding 1 million kW. The project's successful construction and operation have played a crucial role in driving the development of China's offshore wind power industry.
Future Outlook
The Jiangsu Rudong Offshore Wind Farm Phase II is expected to continue serving as a leading example, fostering high-quality development within China's offshore wind power industry.
Jiangsu Rudong Offshore Wind Farm Phase II, China's Technology and Contribution
Project Overview
Jiangsu Rudong Offshore Wind Farm Phase II is located along the eastern coast of Jiangsu Province, about 40 kilometers from the shoreline, with a total installed capacity of 800 megawatts. It is currently China's largest single offshore wind farm in terms of capacity. Construction began in December 2021 and all turbines were operational by December 2023.
China's Technology and Contribution
China has contributed several key technologies to the Jiangsu Rudong Offshore Wind Farm Phase II project, including:
- Large-scale offshore wind turbines: The project utilizes 16-megawatt offshore wind turbines independently developed by China, boasting higher efficiency and lower costs.
- Offshore wind farm design and construction: The project employed China's self-developed technologies for offshore wind farm design and construction, effectively addressing complex sea and wind conditions.
- Offshore wind farm operation and maintenance (O&M): China's independent O&M technologies for offshore wind farms ensure the safe and stable operation of the wind farm.
Project Significance
The completion and operation of Jiangsu Rudong Offshore Wind Farm Phase II marks a significant breakthrough in China's offshore wind power technology and contributes significantly to the development of China's offshore wind power industry. The project will effectively alleviate the structural contradictions in China's energy mix, promote clean energy development, and support China's goal of achieving peak carbon emissions and carbon neutrality.
Details of Technologies and Contributions
Technology/Contribution | Specific Content |
---|---|
Large-scale offshore wind turbines | Rated capacity of 16 megawatts, utilizing permanent magnet direct drive technology for higher efficiency and lower costs |
Offshore wind farm design and construction | Employs technologies like floating foundations and jacket structures to effectively handle complex sea and wind conditions |
Offshore wind farm operation and maintenance | Utilizes intelligent O&M platforms and big data analysis to ensure the safe and stable operation of the wind farm |
References
- Jiangsu Rudong Offshore Wind Farm Phase II Project Commences Construction:
- Jiangsu Rudong Offshore Wind Farm Phase II Project Fully Operational
- Major Breakthrough Achieved in China's Offshore Wind Power Technology
Jiangsu Rudong Offshore Wind Power Project Phase II: Cooperation and Investment
Project Overview
- Project Name: Jiangsu Rudong Offshore Wind Power Project Phase II
- Project Location: Rudong City, Jiangsu Province, China
- Project Scale: 800 megawatts (MW)
- Total Investment: Approximately 10 billion yuan (RMB)
- Project Content: Construction of 80 10MW offshore wind turbines
- Project Construction Period: 2023 to 2025
- Project Completion Date: 2025
Project Cooperation and Investment
The project is jointly invested and constructed by China Huaneng Group Co., Ltd., China Guodian Corporation, and Jiangsu Electric Power Co., Ltd.
Project Cooperation Mode:
- China Huaneng Group Co., Ltd.: Responsible for project development, construction, and operation
- China Guodian Corporation: Responsible for project financing
- Jiangsu Electric Power Co., Ltd.: Responsible for project grid connection
Project Investment Estimation
The total investment of the project is about 10 billion yuan, of which:
- Wind turbine procurement: about 6 billion yuan
- Offshore infrastructure construction: about 2 billion yuan
- Offshore wind farm operation: about 2 billion yuan
Project Benefits
After the project is completed, it can generate about 2.2 billion kilowatt-hours (kWh) of electricity per year, which is equivalent to reducing coal consumption by about 660,000 tons and reducing carbon dioxide emissions by about 1.7 million tons.
- The project can create about 1,000 jobs for the local area.
- The project will promote local economic development and drive the development of related industrial chains.
Project Progress
The project started construction in 2023 and is expected to be completed and put into operation in 2025.
Project Significance
The project is a key project of the national "14th Five-Year Plan" and an important project for the development of offshore wind power in Jiangsu Province.
- The construction of the project will further improve the installed capacity of offshore wind power in Jiangsu Province, optimize the energy structure, and help achieve the goal of carbon peaking and carbon neutrality.
References
- China Huaneng Group Co., Ltd.: https://www.chnenergy.com.cn/
- China Guodian Corporation: https://en.wikipedia.org/wiki/China_Guodian_Corporation
- Jiangsu Electric Power Co., Ltd.: https://www.bloomberg.com/profile/company/KMCBYZ:CH
Table
Project Name | Project Location | Project Scale | Total Investment | Project Content | Project Construction Period | Project Completion Date | Project Cooperation and Investment | Project Investment Estimation | Project Benefits | Project Progress | Project Significance |
---|---|---|---|---|---|---|---|---|---|---|---|
Jiangsu Rudong Offshore Wind Power Project Phase II | Rudong City, Jiangsu Province, China | 800 MW | Approximately 10 billion yuan | Construction of 80 10MW offshore wind turbines | 2023 to 2025 | 2025 | China Huaneng Group Co., Ltd., China Guodian Corporation, and Jiangsu Electric Power Co., Ltd. jointly invest and construct | Total investment of the project is about 10 billion yuan, of which: Wind turbine procurement: about 6 billion yuan Offshore infrastructure construction: about 2 billion yuan Offshore wind farm operation: about 2 billion yuan | After the project is completed, it can generate about 2.2 billion kWh of electricity per year, which is equivalent to reducing coal consumption by about 660,000 tons and reducing carbon dioxide emissions by about 1.7 million tons. The project can create about 1,000 jobs for the local area. The project will promote local economic development and drive the development of related industrial chains. | The project started construction in 2023 and is expected to be completed and put into operation in 2025. | The project is a key project of the national "14th Five-Year Plan" and an important project for the development of offshore wind power in Jiangsu Province. The construction of the project will further improve the installed capacity of offshore wind power in Jiangsu Province, optimize the energy structure, and help achieve the goal of carbon peaking and carbon neutrality. |
Summary
The Jiangsu Rudong Offshore Wind Power Project Phase II is a major project in the field of clean energy. After its completion, it will have a positive impact on the local economic development, environmental protection, and energy security. The project is in line with the national strategy of vigorously developing renewable energy and helps to achieve the goal of carbon peaking and carbon neutrality. Let's look forward to the smooth construction and commissioning of the project!