China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture共和 County (Gonghe) 1 Million Kilowatt Photovoltaic Power Project
Project Overview
The China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County 1 Million Kilowatt Photovoltaic Power Project is one of the first batch of large-scale base projects in China and a key project for Qinghai Province. The project commenced full construction on June 10, 2022, covering an area of 1,660 hectares with a total installed capacity of 1 million kilowatts and a total investment of 4.81 billion yuan.
Project Construction
The project is being built in four phases. The first and second phases, totaling 500,000 kilowatts, were put into operation in June 2023. The third phase, with 300,000 kilowatts, is under construction and is expected to be operational by June 2024. The fourth phase, with 200,000 kilowatts, is planned to be operational by June 2025.
Project Benefits
Upon completion, the project will have an annual average power generation of 1.78 billion kilowatt-hours, saving 543,900 tons of standard coal annually. This translates to a reduction of approximately 1.4843 million tons of carbon dioxide emissions per year.
Project Significance
The construction of this project is of great significance for optimizing Qinghai Province's energy structure, promoting clean energy development, and driving rural revitalization.
Project Highlights
- The project utilizes advanced photovoltaic modules and inverters. The photovoltaic modules boast a conversion efficiency of 21.6%, and the inverters reach an efficiency of 98.5%.
- The project construction incorporates "Internet +" technology, achieving information-based management throughout the entire project lifecycle.
- Upon completion, the project is expected to create approximately 1,000 jobs for the local community.
Project Future
Once completed, the project will become the largest photovoltaic power project in Qinghai Province and even the western region, making a significant contribution to Qinghai's clean energy development.
The History of the China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW photovoltaic power project
The history of the China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW photovoltaic power project can be traced back to 2019, when the Qinghai Provincial Development and Reform Commission approved the project. The project is located in the共和县塔拉滩, with a total investment of 481 million yuan and a total installed capacity of 100MW. The project is divided into three phases, and the construction of the first phase of 50MW was started in June 2020. The second phase of 50MW was started in December 2020. The project was fully connected to the grid and put into operation in September 2022.
The project is a key project of the Qinghai Provincial Government and is also a major project of the China Huatian Group. The project is of great significance to promoting the development of the photovoltaic industry in Qinghai Province and helping to achieve the goal of "carbon peak and carbon neutrality".
Here is a timeline of the project:
- 2019: The project was approved by the Qinghai Provincial Development and Reform Commission.
- June 2020: The construction of the first phase of 50MW was started.
- December 2020: The construction of the second phase of 50MW was started.
- September 2022: The project was fully connected to the grid and put into operation.
The project has the following benefits:
- It can effectively promote the development of the photovoltaic industry in Qinghai Province.
- It can help to achieve the goal of "carbon peak and carbon neutrality".
- It can improve the local ecological environment.
- It can promote the local economic development.
The project is a major achievement in the development of the photovoltaic industry in Qinghai Province. It has important practical significance for promoting the transformation and upgrading of the energy structure, protecting the ecological environment, and promoting the sustainable development of the economy and society.
Specifications of the China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW photovoltaic power project
中国华天集团青海海南藏族自治州共和县(共和) 100万千瓦光伏发电项目 Specification
Here are the specifications of the China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW photovoltaic power project:
- Project name: China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW photovoltaic power project
- Project location: Gonghe County, Hainan Tibetan Autonomous Prefecture, Qinghai Province, China
- Total investment: 481 million yuan
- Total installed capacity: 100MW
- Project scale: The project covers an area of 1,660 hectares and consists of 315 sub-arrays.
- Project technology: The project adopts single-crystal silicon photovoltaic modules and Huawei inverters.
- Project construction: The project was constructed in three phases. The first phase of 50MW was started in June 2020 and was put into operation in December 2020. The second phase of 50MW was started in December 2020 and was put into operation in June 2021. The project was fully connected to the grid and put into operation in September 2022.
- Project benefits: The project can generate 149.4 million kWh of electricity per year, which can save 464,600 tons of standard coal and reduce 1.2266 million tons of carbon dioxide emissions per year. The project can also promote the local economic development and create jobs.
China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW Photovoltaic Power Project Specifications
Specification | Description |
---|---|
Project Name | China Huatian Group Qinghai Hainan Tibetan Autonomous Prefecture Gonghe County (Gonghe) 100MW Photovoltaic Power Project |
Project Location | Gonghe County, Hainan Tibetan Autonomous Prefecture, Qinghai Province, China |
Total Investment | 481 million yuan |
Total Installed Capacity | 100MW |
Project Scale | 1,660 hectares; 315 sub-arrays |
Project Technology | Single-crystal silicon photovoltaic modules, Huawei inverters |
Project Construction | Three phases: <br> - Phase 1 (50MW): Started June 2020, operational December 2020 <br> - Phase 2 (50MW): Started December 2020, operational June 2021 <br> - Full grid connection and operation: September 2022 |
Project Benefits | - Annual electricity generation: 149.4 million kWh <br> - Standard coal saved annually: 464,600 tons <br> - Annual CO2 emissions reduction: 1.2266 million tons <br> - Promotes local economic development and job creation |
The project is a key project of the Qinghai Provincial Government and is also a major project of the China Huatian Group. The project is of great significance to promoting the development of the photovoltaic industry in Qinghai Province and helping to achieve the goal of "carbon peak and carbon neutrality".